Newark Airport

At the request of the PANYNJ, Mr. Giaramita joined this $350 million design/build automated airport monorail project when it was approximately 70% complete, assuming the role of Assistant Site Manager for the DBOM Team. He oversaw the management of steering this troubled project back on track, as it was already more than one year behind schedule and $150 million over budget. This was executed by managing various problem areas on this automated people mover project; namely, directing engineering, procurement, management and field construction forces to meet project goals. Additional responsibilities included managing the automated train control hardware/software subcontractor and directing the scheduling effort to complete this project on the completion date established over 14 months earlier.